An applicant seeking approval of an activity permitted on review shall follow the steps outlined below. The common review procedures for each stage are set out in Article 5 of this Title.

6-111.A. Pre-Application Conference. The applicant may attend a pre-application conference prior to submission of an application.

6-111.B. Submit Application. The applicant shall submit a complete application to the Planning Director containing those materials listed in Section 6-112 of this Division.

6-111.C. Staff Review and Referral. The Planning Director shall review and refer an application in conformance with Section 5-203.A and B of this Title.

6-111.D. Public Notice. Public notice that P&Z will conduct a hearing to consider the application for approval of an activity permitted on review shall be a Level 4 Notice according to the provisions of 5-204.C.

6-111.E. Staff Report. A staff report shall be prepared and made available as called for in Section 5-203.C of this Title.

6-111.F. Public Action By P&Z. P&Z shall hold a public hearing to review an application and render a decision thereon in accordance with Section 5-206.C and D of this Title.

6-111.G. Actions Following Approval. An applicant may obtain a building permit following approval of the activity permitted on review only after the execution and recordation, if necessary, of all documents memorializing or required under the approval, and the payment of fees, as specified under Section 5-209 of this Title. and the filing and, if applicable, recordation of any documents required by the approval.

6-111.H. Notice. A public notice announcing the final approval of the permitted use on review shall be published in accordance with the provisions of Section 5-208.H of this Title.

6-111.I. Vesting. An approved final plan for a permitted use on review, except for a home occupation, shall constitute a site specific development plan.

(Ord. 1561, 2023)