An applicant seeking approval of a final PUD shall follow the steps outlined below. The common review procedures for each stage are set out in Article 5 of this Title.

6-311.A. Pre-Application Conference. The applicant may attend a pre-application conference prior to submission of an application.

6-311.B. Submit Application. The applicant shall submit a complete application to the Planning Director containing those materials listed in Section 6-312 of this Division.

6-311.C. Staff Review and Referral. The Planning Director shall review and refer an application in conformance with Sections 5-203.A and B of this Title.

6-311.D. Approval of Final Plan. If the final plan and proposed plat conform with the approved preliminary plan, then it shall be finally approved by the Planning Director and P&Z Chairperson. If the final plan or plat proposed or requested, does not substantially conform with the approved preliminary plan final plan or plat, they shall be remanded to P&Z for a new review and preliminary approval at a public hearing after which it shall be subject again to final approval as provided herein.

6-311.E. Filing. The Mayor, P&Z Chairperson, Planning Director, and Town Engineer shall sign approved final plans and plats within a reasonable time after submission of all required documents and evidence that all applicable conditions in the PUD plan and any improvements agreement have been met. Upon prepayment by the applicant of the County Clerk’s recording fee the Planning Director shall record the executed final plat together with any improvements agreement in the office of the Clerk and Recorder.

6-311.F. Notice. Public notice announcing the approval of a final PUD plan and plat shall be published in accordance with the provisions of Section 5-208.H of this Title.

6-311.G. Vesting. An approved final PUD plan and or plat shall constitute a site specific development plan; as such, it is subject to the vested rights provisions of Section 5-208 of this Title.

6-311.H. Map Notation. Following recordation of the final plan/plat, the Planning Director shall place a notation on the Official Zone District Map that the subject parcel is a PUD.

6-311.I. Obtain Building Permit. An applicant may obtain a building permit for development or construction as authorized under a final PUD approval only after the final plat and any improvements agreement have been approved, publicly noticed, executed, and filed of record, and all prerequisite conditions of approval satisfied, including the payment of all fees, as specified under Section 5-209 of this Title.